7.18.7    Download Schedule from Project Manager

Schedule changes will be downloaded to the SCADA Node without stopping the SCADA node. This can be done from any configuration page in the Alarm Management system.

A dialog box prompts the user to confirm the Download Schedule to SCADA Node.  All "submitted" changes made to the scheduler are downloaded.

All Manual ON or Manual OFF states are also downloaded.

To download a change to the SCADA node from Project Manager:

 

1.                      Login to Project Manager

2.                      Select Project and SCADA Node.

3.                      Select Scheduler from SCADA Node main page.

4.                      Make the desired change in Holiday, Time, Worker Group, Alarm Group and the Relationship

5.                      Press the "Submit" button

6.         Click to Download to SCADA Node.

 

 Select OK at the prompt to Download Scheduler